Earlier this week, the Town of Troy and St. Croix County have begun the work to rehabilitate Delander Drive and Skyline Road.  Below, you will find a tentative work schedule for completing the road rehabilitation projects. 

 

            End of July                 Roads will be widened

            August 13th – 16th       2-3” of Crush rock will be laid on top of current black top.

August 20th – 23rd       Mill machine will come in and mill both roads, then shaping will take place to prepare for paving. Paving will take place shortly after shaping.  Two lifts of blacktop will be laid, 1 ½” each lift. 

August – September   Completion of project, which includes shouldering of roads and reinstallation of mailboxes.

 

Please note that this is a tentative schedule and delays may occur due to weather or other circumstances outside of the Town’s control. 

 