COULEE TRAIL UPDATE: Access Closures – Revised Schedule
Culvert replacement work on the Coulee Trial rehabilitation project has been rescheduled by one day and will now take place later this week and into early next week.
Updated Access Changes for Prominence Way and Coulee Trail:
- Friday, July 11: Crews will begin work on the eastern culvert crossings, requiring all access to Prominence Way to use Coulee Trail from the west (via Old Highway 35).
- Monday, July 14: Work will move to the western crossings, and all Prominence Way traffic will need to use Coulee Trail from the east (via County Road U).
Driveway Culvert Replacements:
Driveway culverts for homes that directly access Coulee Trail within the project area are now scheduled for Tuesday, July 15. The contractor will communicate directly with affected property owners in advance of any temporary driveway access restrictions.
Reminder: Coulee Trail Rehabilitation Project
This project includes rehabilitation of Coulee Trail from Forest Rise to County Road U, and is expected to continue through mid-August, weather permitting.
What to Expect During Construction:
- Traffic Disruptions: Temporary closures, access shifts, and flagging operations will continue through various phases of work.
- Driveway & Mailbox Access: Maintained wherever possible. Temporary driveway closures will be communicated in advance.
- Contractor Coordination: The contractor will make every effort to notify affected residents prior to any planned disruptions.
- General Disruption: Expect increased construction activity, dust, and equipment throughout the corridor during active work periods.
We appreciate your continued patience and cooperation as we work to complete this necessary town road improvement.
For questions or concerns, please contact the Town Administrator, David Carlson, at 715-425-2665, ext 101