Dec 19. Informal Discussions and Coffee With Town Chairperson, Doug Rowen: Informal Discussions and Coffee with Town Chairperson, Doug Rowen Saturday, December 19, 2026  8:00 AM – 11:00 AM Troy Town Hall 654 Glover Road Focused Topics:         Proposed changes to City of River Falls Extraterritorial Subdivision Ordinance and Boundary                                                 Troy Fire Service Optimization – January 1, 2027 Troy Board Chairperson, Doug Rowen, will be available on December 19, 2026 at the Troy Town Hall from 8:00-11:00 for informal discussions with residents. Feel free to stop by during that time if you have questions or topics relative to Troy that you would like to discuss. Current Projects – Town of Troy Other topics from past meetings: Other popular topics from past discussions: How can Troy maintain it’s rural character for the long term? How much property tax does the Town receive and how is the Town Budget determined? How and why is Troy property annexed into the Cities of River Falls and Hudson? Town Hall expansion plans Anything else that is on your mind…  

COULEE TRAIL UPDATE: PAVING PREPARATION AND ASPHALT WORK SCHEDULED

COULEE TRAIL UPDATE: Paving Preparation and Asphalt Work Scheduled

The Coulee Trail rehabilitation project is moving into the next phase. Paving preparation work will continue this weekend. Please plan accordingly and consider using alternate routes to avoid active work areas.

Upcoming Construction Activity:

  • Saturday, July 19: General pavement preparation work will be ongoing. The road base will be removed and repaired near the Forest Rise intersection on the west end of the project. Traffic will be restricted to one lane during that time.
  • Monday, July 21: Paving of the first lift of asphalt is scheduled. Construction flaggers will be on site to manage traffic flow around active paving areas. Access through the corridor may be temporarily restricted or delayed, but local traffic will be accommodated. Paving work may continue on Tuesday to complete the scheduled work.
  • Following Initial Paving: Site restoration work – including shoulder shaping, ditch work, and reestablishment of vegetation – will begin after the first asphalt lift is installed. Once restoration is substantially complete, the paving crew will return to install the final surface lift of asphalt.

Project Status Summary:

The project continues to progress on schedule. Recent work has included culvert installation, subgrade preparation, aggregate base placement, and erosion control measures. We appreciate everyone’s continued patience and cooperation as we work through these final stages.

For questions or concerns, please contact Town Administrator David Carlson at 715-425-2665, ext. 101.