St. Annes Parkway Rehabilitation

Work on the St. Annes Parkway Rehabilitation project is moving into active construction phase. Below is the schedule for the upcoming work. Dates are current as of this notice but may shift due to weather or field conditions. 

Date 

Work Activity 

Aug. 3 

Traffic control set up 

Aug. 4-5 

Pavement pulverizing 

Aug. 6-7 

Driveway removal 

Aug. 10-14 

Curb and gutter installation 

Aug. 17 

Driveway concrete poured 

Questions? 

Town of Troy — David Carlson, Town Administrator 

(715) 425-2665  •  [email protected] 

Project Representative — Robert Jones, Cedar Corporation 

(715) 308-4148  •  [email protected]